🚀 2026 New Year Kickoff:Start strong — get 25% off for life25% off for life! Free Trial

Construction Scheduling

Construction Scheduling: Make It Real, Make It Useful

A schedule is not a decorative Gantt chart. It is a management system for time, money, and risk. In Australia, it also becomes evidence for variations, EOTs, and disputes—so it must be logical, maintained, and defensible.

1. The Minimum Standard for a Professional Program

  • Clear WBS: break down by building area and trade. If you can’t assign a foreman and a subcontractor to a task, it’s not specific enough.
  • Logical links: use true dependencies (FS/SS/FF) instead of date constraints that hide problems.
  • Milestones: approvals, service connections, inspections, handover, and procurement releases.
  • Procurement integration: long-lead items must appear as activities (selection → shop drawings → manufacture → delivery).

2. Durations: Why Most Programs Lie

Programs blow out because durations are optimistic and ignore real constraints: access, stacking trades, wet weather, inspections, curing times, and supplier lead times.

Practical tip: Build your duration library from actuals. Update it job by job. That’s how “programming” becomes a competitive advantage.

3. Updating: A Program That Isn’t Updated Is a Work of Fiction

  • Update weekly (not monthly) on active sites.
  • Record progress based on site evidence (completed and inspected), not “we’re basically done”.
  • Re-forecast: adjust the remaining duration based on actual productivity.

4. The Output That Matters

  • Look-ahead plan: 3–6 weeks, trade by trade, with constraints visible.
  • Decision register: items that will delay the program if not resolved.
  • Procurement tracker: what must be ordered this week to protect the critical path.